15.20.110 Final inspection.

The electrical inspector shall be notified when any electrical work is complete and ready for final inspection and he or she shall, as soon as practicable, inspect such work, and if such work conforms with this chapter, the inspector shall release the work to the utility company for service. A certificate of inspection shall be issued after a showing that such work meets the requirements of this chapter. It is unlawful for any person, firm or corporation to make a connection for a source of electric energy to any electric wiring, apparatus, appliances or equipment for which a permit is required until approved by the electrical inspector; provided, that the inspector may authorize temporary connections for the purpose of testing any such work or for other reasons requiring electrical current when the same shall not be hazardous to life or property. (Ord. G-770 § 2 (part), 1993: prior code § 5-411)